"B-Area Chiller Plant"
Savannah River Site - Aiken, SC
 
Client:

Department of Energy

Contract Type:

Design/Build

Scope of Work:

Mechanical included new 2,200 ton capacity chiller facility with all associated equipment and piping, setting of pumps and cooling tower. Distribution system was over 22,000 linear feet of pre-insulated pipe.The Chiller Facility currently serves 6 existing buildings at SRS.

Location:

Savannah River Site - Aiken SC

Project Size:

Distribution System - over 22,000 linear feet

Construction Cost: